Transfer semifinished material to SL after confirmation of an operation

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #22736
    Anonymous
    Inactive

    Hi all, we have a finished material say X which is made up of SF materials say Y & Z. Y is made up of RM A & B. Z is made up RM say C & D. we have 3 operations in our routing. SF material Y is made after 2nd operation and is stored in a SL. how can i map this in system.

    #22860
    Edward T
    Participant

    Hi,

    First you need to create BOMs
    SF Y with component A, B
    SF Z with component C, D
    FG X with component Y, Z

    Then for each material BOM you need to create routing/ recipe.
    Recipe for X, Y, Z
    the operation sequence need to define based on your production process in sequence,
    means if you said SF Y produce first, then SF Z, then in Recipe for X you need to put material assignment Y in previous operation before operation with Z.
    Hope it will help.

    Regards,
    Edward