SAP Work Center and Cost Center Integration

SAP Work Center and Cost Center IntegrationWelcome to the tutorial about SAP Work Center and Cost Center Integration. This tutorial is part of the SAP PP training course. You will learn about the relationship between work centers and cost centers in SAP, how to use activity types and define activity prices. Also, we will discuss a complete example of calculating activity cost in product costing.

What is a Cost center in SAP?

SAP cost center can be created for each organization function or department to record the cost incurred which contribute to a company’s profitability indirectly. Here some of the cost center categories generally used in SAP

  • Production
  • Sales
  • Administration
  • Service Cost center

In SAP production planning, each work center will be assigned to one cost center. For every activity type defined in a work center, an activity rate will be maintained in the cost center. SAP system uses this information to calculate activity cost for an operation.

We can assign a work center to only one cost center. But we can assign several work centers to one cost center.

Example

Consider a steel making industry where steel billets are manufactured from DRI steels, steel scrap, etc. A furnace operates on 120 T per day and the following activities are performed in furnace to make the molten steel metal:

  1. Furnace operation (charging, melting, slagging and tapping)
  2. Labor hours

In this case, we can define two activity types in the work center EAF01 (electric arc furnace) and assign them to work center EAF01. The work center is assigned to the cost center F1000.

Activity rate for each activity (furnace hours and labor hours) are maintained against the cost center. Planned furnace hours and labor hours are maintained for the base quantity of 120 T (furnace capacity) in a routing. Formula for each activity (furnace hours and labor hours) are maintained in a work center.

Activity Cost Calculation Formula
Activity Cost Calculation Formula

When a production order is created in the SAP system, it uses the above information to calculate the activity cost.

Example of SAP Work Center and SAP Cost Center Integration
Example of SAP Work Center and SAP Cost Center Integration

Activity Types in Costing

Activities produced in a cost center are created as activity types. In the above example, two activities are produced in a furnace which are machine hours and labor hours. We can create these two activity types and assign them to the cost center of furnace. The same two activity types can also be assigned to cost centers of ladle and casting.

Activity Types in SAP Cost Centers
Activity Types in SAP Cost Centers

Activity Price of Activity type

Activity price will be defined for each activity type and cost center manually. In this example, even though we have similar activity types for all three cost centers, activity price will be different for each cost center. The activity price is defined in the transaction KP26.

Activity Cost in Product Costing

In general, product cost in SAP comprise of three primary components:

  1. Raw material or component cost
  2. Activity cost
  3. Overhead cost

Here, activity cost is calculated based on work centers, cost centers and activity prices. The SAP system calculates the activity cost by multiplying the activity price to quantity of operations.

Example of Activity Cost in Product Costing

Let’s consider an example. A work center furnace produces molten metal for casting formation. This work center has the following activities:

  1. Setup
  2. Machine
  3. Labor
SAP Work Center Assignment to SAP Cost Center
SAP Work Center Assignment to SAP Cost Center

The work center is assigned to the cost center (4230) and each activity (setup, machine and labor) is assigned with an activity type (1422, 1420 and 1421).

Now, let’s look at activity price calculation. Activity prices are maintained for the cost center (4230) and activity types (1422, 1420 and 1421) in the transaction KP26 by a controlling person.

Setup Activity Price (Cost Center 4230 and Activity Type 1422)
Setup Activity Price (Cost Center 4230 and Activity Type 1422)
Machine Activity Price (Cost Center 4230 and Activity Type 1420)
Machine Activity Price (Cost Center 4230 and Activity Type 1420)
Labor Activity Price (Cost Center 4230 and Activity Type 1422)
Labor Activity Price (Cost Center 4230 and Activity Type 1422)

Next, let’s check routing details of the material. It will specify how many units of each activity are required for manufacturing a base quantity of this material.

SAP Routing for a Material (Transaction CA01)
SAP Routing for a Material (Transaction CA01)

We perform a costing run for the material CAST01 in transaction CK11N to see how the SAP system calculates product cost for this material.

Material Cost Estimate (Transaction CK11N)
Material Cost Estimate (Transaction CK11N)

On the picture above, the highlighted area is the activity cost calculated by the system based on the information maintained in the work center (transaction CR01), activity price (transaction KP26) and routing (transaction CA01).

The calculation is performed according to the following formula:

Machine hour activity cost = Machine activity price / Unit * Quantity from Formula

Quantity = ((120/100) *10)/60 = 0.200 Hour

Activity Price = 2246.88/100 = 22.47

Activity Cost = 22.47 * 0.200 = 4.49 EUR

For other activity types calculation is performed in a similar manner.

Did you like this tutorial? Have any questions or comments? We would love to hear your feedback in the comments section below. It’d be a big help for us, and hopefully it’s something we can address for you in improvement of our free SAP PP tutorials.

Navigation Links

Go to next lesson: SAP Task List

Go to previous lesson: SAP Work Center Capacity

Go to overview of the course: SAP PP Training

17 thoughts on “SAP Work Center and Cost Center Integration”

  1. Very good and easy to understand tutorial, so far has been understood, I hope next lesson. Thank you

  2. Hi, where is the “10” in quantity coming from? and how do you calculate the 2246.88 in Activity Price?

    Thanks

      1. Hello,
        I have a question. For the activity price calculation why you divided the average price of activity by 100?
        Thank you

      2. Thanks for the comment ! The answer is 100 is base quantity from routing and to obtain unit price it was divided by 100

  3. Sir,
    I am not receiving SAP PP training emails for i kindly request you to send me the mails. I have completed training till 1.5 – SAP Work Center and Cost Center Integration. Hope you will send me the rest and will help me in completing the course.

  4. Sir,able to understand and easy to follow.
    Thank you for sending PP notes. Please send the next lesson. Thank you

  5. Hey there!
    I’m not receiving the lessons from PP training anymore! I’ve completed the training till 1.5 lesson after that no more lessons received.

  6. I am from FICO side, I just I spent more than 11 hours trying to find why in CK11N one work center was not costed.
    Thanks to your tutorial, in less than 10 minutes I found that one data was missed in CA01, so I fix it and now the material is fully costed. Why I didn’t found it earlier?
    Thank you so much!

  7. Well descriptive !!

    But I have a query. Beginning of the blog there is a formula mentioned for the “Furnance activity cost”, is the same applied anywhere down in the calculation you’ve shown?

  8. If I change the Work Centre Capacity Tab, Processing Formula from SAP006 to SAP009 (FLAT and not scaled with changes in quantity of parts run), will that affect the calculation of per unit costing ?

  9. We want to use Work Centers for planning simulation.
    In KP26 you can assign a DIFFERENT rate to the SAME cost center activity type by using different planning versions.
    However when you link the Cost Center to the Work Center it appears to always use the version zero rate. I want to do planning simulation using rates from version 000, 001, and ABC. Is there a way to point a work center to a different planning version rate.

    Example: Cost Center Activity type Version Rate
    test00 xyz 000 20.00
    test01 xyz 001 24.00
    test02 xyz ABC 25.00

  10. It’s a great blog and very detailed. I have a question related to costing of the production order.

    1) I have an operation in the production order whose start date and end date is in May 2023 . When I am saying start date and end date I mean the confirmed start and confirmed end date. But if I go to the administrative tab of the confirmation it shows as entered by some user and entered on June 2023. Now the cost of the production order for this operation is shown in June 2023 and not May which was the real confirmed start and end date. Can anyone tell me why and what is the possible solution of I want the cost to be calculated in May

Leave a Reply

Do you have a question and want it to be answered ASAP? Post it on our FORUM here --> SAP FORUM!

Your email address will not be published. Required fields are marked *